List of Projects in Iran
Category A
no projects
Category B
JBIC's Project Categorization
JBIC puts projects
into one of four categories, A, B, C, or FI, in accordance
with the extent of the environmental impact(s) and/or JBIC's
involvement in the project. Category A and B projects are
expected to have significant impacts on the environment (for
more detailed explanations, see
JBIC page
Below is a list of all the projects that JBIC has classified
as Category A or B since JBIC's
new guidelines were established on October 1, 2002. (The
full implementation of the guidelines started on October 1,
2003.) @This list is a translation of the list provided in
Japanese on JBIC's official website.
You can inquire to JBIC for more information on each project,
with the Inquiry Number indicated below.
E-mail inquiries to JBIC: kankyoshakai@jbic.go.jp
Category B Projects
| Manufacturing
plant of ethylene glycol |
| Location |
Kohgiloyeh-va-Boyerahmad, Gachsaranmm |
| Inquiry No. |
2005-0155 |
| Loan Scheme |
IFO |
| Date of information
disclosure on JBIC Website |
September 12, 2005 |
| Present
Status of Project |
Environmental review is ongoing |
| Project Outline and Sector
|
To construct manufacturing plant of ethylene glycol
that produces 550,000tons/year. |
| Reasons for
Category Classification (Based on gIllustrative list of
Sensitive Sectors, Characteristics and Areash of Guidelines)
|
This project does not fall under the sensitive sectors,
characteristics and regions and thus does not have significant
adverse impact on the environment. |
| Relevant Documents Available
at JBIC Head Office in Tokyo |
@ |
| Application of New JBIC
Guidelines |
fully applied |
| Additional Information |
@ |
| High-density
polyethylene Plant |
| Location |
Bandar Assaluyeh |
| Inquiry No. |
2005-098 |
| Loan Scheme |
IFO |
| Date of information
disclosure on JBIC Website |
June 7, 2005 |
| Present
Status of Project |
|
| Project Outline and Sector
|
To construct High-density polyethylene Plant |
| Reasons for Category Classification
(Based on gIllustrative list of Sensitive Sectors, Characteristics
and Areash of Guidelines) |
- not sensitive area illustrated by guideline
- not significant adverse impact |
| Relevant Documents Available
at JBIC Head Office in Tokyo |
@ |
| Application of New JBIC
Guidelines |
fully applied |
| Additional Information |
@ |
| New
construction of Ethylene Glycol Plant |
| Location |
Kharg Island |
| Inquiry No. |
2005-032 |
| Loan Scheme |
IFO |
| Date of information
disclosure on JBIC Website |
March 1, 2005 |
| Present
Status of Project |
Loan Agreement was signed on March 21, 2005 |
| Project Outline and Sector
|
To construct Ethylene Glycol Plant |
| Reasons for Category Classification
(Based on gIllustrative list of Sensitive Sectors, Characteristics
and Areash of Guidelines) |
- not sensitive area or characteristics illustrated
by guideline
- not significant adverse impact |
| Relevant Documents Available
at JBIC Head Office in Tokyo |
@ |
| Application of New JBIC
Guidelines |
fully applied |
| Additional Information |
@ |
| High-density
Polyethylene Plant in Ilum Project |
| Location |
Surburb of Ilum City, in the State of Ilum |
| Inquiry No. |
2004-114 |
| Loan Scheme |
IFO |
| Date of information
disclosure on JBIC Website |
August 9, 2004 |
| Present
Status of Project |
Loan Agreement was signed on October 18, 2004 |
| Project Outline and Sector
|
Polyethylene Plant |
| Reasons for Category Classification
(Based on gIllustrative list of Sensitive Sectors, Characteristics
and Areash of Guidelines) |
This project is not fallen under eIllustrative list
of sensitive sectors, characteristics and areas' and it
does not have significant adverse impact on environment. |
| Relevant Documents Available
at JBIC Head Office in Tokyo |
@ |
| Application of New JBIC
Guidelines |
fully applied |
| Additional Information |
@ |
| Fertilizer
Plant the 2nd Phase Project |
| Location |
@ |
| Inquiry No. |
2004-039 |
| Loan Scheme |
IFO |
| Date of information
disclosure on JBIC Website |
March 11, 2004 |
| Present
Status of Project |
Loan Agreement was signed on April 9, 2004. |
| Project Outline and Sector
|
Export of fertilizer plant |
| Reasons for Category Classification
(Based on gIllustrative list of Sensitive Sectors, Characteristics
and Areash of Guidelines) |
No factor to be classified as Category A |
| Relevant Documents Available
at JBIC Head Office in Tokyo |
@ |
| Application of New JBIC
Guidelines |
Fully Applied |
| Additional Information |
JBIC